Aerial view of the standing seam roof nearing completion, crew working at the ridge
Build 02 · Standing seam roof · April 2025

Norwood Ridge

Lenoir, NC Completed 2025
Register
01The build

A 3,240-square-foot house on a sloped lot off Norwood Street. The grade drop across the footprint was just over eight feet, which decided the foundation: a block stem wall stepped in four courses rather than one tall poured wall, so the crawl space stays ventilated without retaining the uphill side.

Read more

The roof is standing seam over a vented assembly, installed in April before the envelope was closed, which kept the framing dry through a wet spring. Kitchen millwork was built in our own shop over six weeks while the house was being sheathed, so cabinets were set the week after drywall finish instead of eight weeks later.

Framing, roofing and cabinetry were carried out by our crews. Mechanical, electrical and plumbing were subcontracted to trades we have used on every build since 2024.

Location
Lenoir, North Carolina
Year
2025
Area
3,240 sf · 301 m²
Architecture
In-house design
Structure
Consulting PE, Caldwell County
Scope
Full build · cabinetry · exposed timber
Duration
Jan – Sep 2025 · 9 months
Status
Completed
02Sequence
Floor joists set over the stepped block foundation, bare winter trees behind
01 — Floor systemJoists set over the stepped stem wallJan 2025
Crew framing walls and installing sheathing, mountains in the distance
02 — Wall framingExterior walls up, sheathing and house wrap in progressMar 2025
Standing seam roof panels being fixed at the ridge
03 — RoofStanding seam over a vented assemblyApr 2025

Millwork built while the house was still open.

Running the shop in parallel with the envelope is what compresses the back half of a build. The drawer banks below were laid out in April; they were set in place in June.

Two carpenters marking out a bank of drawers in the shop
04 — ShopDrawer bank layoutApr 2025
Two carpenters setting the kitchen island under a vaulted ceiling
05 — Cabinet setIsland and perimeter run, one week after drywall finishJun 2025
03Archive · 9 of 214 frames
Jan · Joists Mar · Framing Apr · Roof Apr · Shop Jun · Cabinets Oct · Site Jul · Structure Aug · Porch Nov · Interior
Request this archive

The full set of 214 frames is handed to the owner and the architect at closeout.

I treat every project with care and precision, as if building for my own family.

Taking on builds for spring 2026 · 2 slots

Building something like Norwood Ridge?

Sloped lot, exposed structure, millwork in the same contract. Tell us the site and we will tell you what it takes.